对无节奏流水施工的工期优化问题进行了研究,结合流水施工基本参数和无节奏流水施工的特点,分析了"潘特考夫斯基法"对工期的确定,将矩阵法应用到工期优化中,通过对施工段施工顺序的优化,达到了无节奏流水施工工期优化的效果。
This paper researched the optimization of the construction period of non-rhythm flow process. This paper firstly analyzed the construc-tion period by paterkovsky method combined with basic parameters of flow process and characterisitics of non-rhythm flow process. Then optimized the construction period of non-rhythm flow process based on matrix method.
出处
《山西建筑》
2017年第17期97-98,共2页
Shanxi Architecture
关键词
流水施工
工期
矩阵法
施工段
flow process, construction period, matrix method, construction section