摘要
针对现有流水施工的组织安排方法还不够完善的问题,提出了一种基于施工段的流水施工组织方法。该方法将同一施工过程在不同施工段上开始的时间间隔作为流水步距进行组织施工。通过实例分析探讨了该方法下流水施工组织过程。结果表明,该流水施工组织方法在特定条件下可缩短施工工期,应用效果良好。
Aiming at the existing flow construction organization arrangement method is not perfect,a flow construction method based on the construction section is proposed.In this method the time interval of the on set construction process of different construction sections is selected as the flow step to organize the construction.Through an example analysis,the organization process of the down-flow construction of this method is discussed.The research shows that this method of organization of flow construction can shorten the construction period and shorten the construction period under certain conditions,and the application effect is good.
作者
宋兆瑜
丁文捷
SONG Zhaoyu;DING Wenjie(Ningxia Branch,Zhongxin International Project Management Co.,Ltd.,Yinchuan 750001,China;School of Mechanical Engineering,Ningxia University,Yinchuan 750021,China)
出处
《宁夏工程技术》
CAS
2021年第1期72-74,共3页
Ningxia Engineering Technology
关键词
流水施工优化
流水步距
时间间隔
流水工期
flowing water construction optimization
flow step
time interval
flowing period