异节拍分层流水施工研究

Different Rhythm Layered Flow Construction
下载PDF
导出
摘要 在确保主导施工过程的施工班组能够连续作业的前提下,从施工时间、施工进度、施工连续性方面,确定异节拍分层流水施工应具备的条件以及工期计算简式。异节拍流水施工有两种方式:连续式、断续式;两种方式有共同性,侧重点也不同,各有优劣。但异节拍流水施工优于其他施工方式。 Under the premise of ensuring that the construction team leading the construction process can continue to work,diff erent rhythm layered fl ow construction should determine the conditions to be available and the duration of the calculation formula from the aspects of construction time,construction progress,construction continuity.There are two ways in the construction:continuous and discontinuous;the two methods have diff erent emphasis despite common features with advantages and disadvantages respectively.Even so,diff erent rhythm layered fl ow construction is better than other construction methods.
作者 宋文学 朱宝胜 Song Wenxue;Zhu Baosheng(Department of Undergraduate Education,Anhui Water Conservancy Technical College,Hefei 231603,China)
出处 《黑河学院学报》 2023年第5期176-177,185,共3页 Journal of Heihe University
基金 安徽省高等学校省级质量工程项目“《建筑施工组织》课程思政示范课程”(2021kcszsfkc168)。
关键词 异节拍 分层流水施工 施工组织 工作面 工期 diff erent rhythm fl ow construction construction organization working face construction period
  • 相关文献

参考文献4

二级参考文献23

共引文献39

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部