摘要 鉴于葛洲坝水电站的水轮发电机组已投产服役了30多年,机组的年平均运行小时数高达6 500 h,机组及其部件出现的老化现象严重,影响机组安全运行,通过分析、比较、研究,在进行设备改造检修的同时,将125 MW机组增容至146 MW,既实现了设备的更新换代,又适应了三峡工程建成后的联合运行。 The units of Gezhouba Hydropower Station have been put into operation for 30 years.The annual average runtime of the units is up to 6500 hours and the units and their parts are aging seriously,which influenced the safe operation of the units.The alteration capacity of the units is increased from 125 MW to 146 MW by means of analysis,comparison,study,while equipment overhaul is carried out,which not only realizes equipment upgrading but also adapts to the joint operation of the Three Gorges project.
出处 《水电与新能源》 2013年第4期4-7,共4页 Hydropower and New Energy
关键词 葛洲坝水电站 水轮发电机组 改造 增容 Gezhouba hydropower station the hydroelectric generating set modification capacity expansion
  • 相关文献

参考文献2

二级参考文献2

  • 1程良骏.水轮机[M].北京:机械工业出版社,1980.. 被引量:2
  • 2白延年.水轮发电机设计[M].上海:科学出版社,1999.. 被引量:2

共引文献4

同被引文献34

引证文献3

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部