摘要
对西安地铁2号线北(大街)~北(门)区间隧道下穿陇海铁路施工阶段的各种风险进行了探讨,重点分析了北(大街)~北(门)区间隧道的工程地质危险因素,盾构法施工的风险,盾构下穿陇海铁路施工控制措施和陇海铁路的加固措施等,可供类似工程借鉴。
Based on the construction of Xi'an Metro Line 2, in which the interval ttmnel between the North Street and the North Gate will pass through the existing Longhai Railway un derground, the interval tunnel's geological risk and the shield construction risk are mainly analyzed, the construction control for shield passing beneath Longhai Railway and the reinforce ment measures are discussed, which will provide a reference for subsequent similar projects.
出处
《城市轨道交通研究》
北大核心
2013年第4期49-53,76,共6页
Urban Mass Transit
关键词
黄土地区
盾构掘进
既有铁路
施工风险
控制措施
loess area
tunneling
existing railway
con-struction risk
control measures