摘要
为合理确定水利工程合同变更中的项目及费用,介绍了工程变更的定义、产生的种类、范围和内容,运用对比合同条款的方法分析了变更细目确定及工程量计算要点,通过工程实例研究了变更项目适用合同单价及不平衡报价、材料价差、工程增量调价处理情况,对变更项目类似合同单价和不适用合同单价提出了解决方法,取得了实践经验,可供同类工程借鉴。
In order to determine contract changing and their costs in hydraulic engineering reasonably,this paper discusses the definition,types,scope and content of engineering change and uses the method of referencing to contract terms to analyze the determination of each project changed and the key points of quantity calculation.Through analyzing engineering examples,it studies the unit price of contract suitable for projects changing and the processing program for unbalanced bidding,material price difference and t...