摘要
为解决高速公路施工进度管理中遇到的问题,利用三维软件建立高速公路3D模型,使用Microsoft Project软件编制施工进度计划,通过Navisworks平台,将高速公路3D模型与Project施工进度计划相链接,形成高速公路4D模型。然后以4D模型为基础搭建基于BIM的高速公路施工进度管理框架,在框架基础上通过工程建设的可视化模拟实现施工进度动态化管理。
In order to solve various problems encountered in schedule management during expressway construction,3D software and Microsoft Project software are adopted,respectively,to build expressway 3D models and compile construction schedules.The expressway 3D model and Project construction schedule were linked to form a 4D model of the expressway through Navisworks platform.Then,a BIM-based expressway construction schedule management framework was built based on the 4D model.And on the basis of the framework,the dynamic management of expressway construction progress was realized through the visual simulation of expressway construction.
作者
杨军红
陈宝光
陈国龙
杨旭
YANG Junhong;CHEN Baoguang;CHEN Guolong;YANG Xu(Power China Road Bridge Group Co.,Ltd.,Beijing100048,China;Changsha Zhongjiao Jingwei Engineering Technology Co.,Ltd.,Changsha,Hunan410000,China;Beijing Zhongjiao Jingwei Highway Cost Technology Co.,Ltd.,Beijing100025,China)
出处
《施工技术》
CAS
2021年第12期25-28,46,共5页
Construction Technology
基金
中电建路桥集团有限公司科技项目(LQ2015-07)。
关键词
高速公路
建筑信息模型
进度
管理
expressway
building information modeling(BIM)
schedule
management