摘要
以超百米水深海域的某油气田开发项目中万吨级组块整体海上浮托安装为例,对组块浮托安装施工原理、施工方案和实际应用效果进行阐述,总结组块浮托安装环境监控、船舶调载、锚泊定位、缓冲对接技术,为后续国内外海上平台组块等结构物的设计和施工提供技术支持。
Taken 10000 t topside floatover in an oil and gas field development project with a water depth of over 100 m as an example,the construction principle,construction scheme and practical application effect of the topside floatover installation are described,and the environment monitoring,ship load adjustment,mooring positioning and buffering docking technologies of the topside floatover installation are summarized,which provides technical support for the subsequent design and construction of offshore platform blocks and other structures at home and abroad.