大跨预应力混凝土连续梁桥悬臂施工结构控制分析 被引量:17

Structural Control Analysis during Construction of Cantilever of Long-span Pre-stressed Concrete Continuous Girder Bridge
下载PDF
导出
摘要 目的研究大跨度预应力混凝土连续梁桥悬臂施工的成桥线形和受力情况,为施工控制提供理论依据,并指导桥梁的设计和施工.方法模拟分析大跨度预应力钢筋混凝土连续桥梁悬臂施工的受力状态和变形特点,得到桥梁结构各个施工阶段的受力状态和变形,利用TDV软件建立桥梁模型,分别采用正装分析法、倒装分析法和无应力状态分析法,对桥梁施工过程进行结构控制分析.结果模拟分析出桥梁结构在各个施工阶段的变形和受力状态以及它们的变化规律,保证桥梁成桥的线形和受力情况符合设计要求.结论根据结构控制原理并结合模拟分析数据特点,正装分析法适用于施工过程中结构应力计算,倒装分析法适用于施工过程中立模标高的确定,无应力状态分析法适用于预测成桥状态下的结构应力和线性情况. The bridge linearity and stress distribution in cantilever of a long-span pre-stressed concrete continuous girder bridge during construction were researched in this paper,which providing theoretical basis for construction control and guidance for bridge design and construction.The stress distribution and deformation characteristic of cantilever-construction of long-span prestressed concrete continuous girder bridge,were analyzed in this paper to obtain the stress distribution and deformation during each construction process.The software,TDV,was utilized in this paper,to analyze and control the bridge construction process based on three models,the orderly-erecting analysis method,the inversion analysis method,and the stress-free state analysis method.De-formation,stress distribution,and corresponding transformation lawof bridge construction during each stage were obtained to ensure that the linearity and stress distribution of bridge could meet the design requirements.In accordance with the principle of structure control and combined with the characteristics of simulation analysis data,conclusions below were made.Firstly,the orderly-erecting analysis method is appropriate for structure stress calculation during construction process.Secondly,the inversion analysis model is appropriate for measurement of elevation.Thirdly,the stressfree state method is appropriate for the prediction on structural stress and linear conditions under the condition of shaping.The characteristics of structure control analysis and application situation were concluded in this paper in the end.
作者 宋福春 张兴 陈冲 李雪莲 SONG Fuchun ZHANG Xing CHEN Chong LI Xuelian(School of Transportation Engineering, Shenyang Jianzhu University, Shenyang, China, 110168 State Grid Lia- oning Electric Power Co. , Ltd. Liaoyang Power Supply Company, Liaoyang, China, 111000)
出处 《沈阳建筑大学学报(自然科学版)》 CAS CSCD 北大核心 2017年第2期226-234,共9页 Journal of Shenyang Jianzhu University:Natural Science
基金 国家自然科学基金项目(51178279) 住房和城乡建设部项目(2015-K5-021)
关键词 正装分析法 倒装分析法 无应力状态分析法 悬臂施工 orderly-erecting analysis method inversion analysis method stress-free state analysis method cantilever construction
  • 相关文献

参考文献8

二级参考文献16

  • 1杨志平,朱桂新,李卫.预应力混凝土连续刚构桥挠度长期观测[J].公路,2004,49(8):285-289. 被引量:51
  • 2楼庄鸿.对预应力混凝土连续刚构几个问题的认识[C]∥中国公路学会桥梁和结构工程分会2004年全国桥梁学术会议论文集.2004:303—306. 被引量:4
  • 3Transguide. http://www.transguide.dot.state.tx.us/lanedata/ . 2007 被引量:1
  • 4M.J. Lighthill,G.B. Whitham.On kinematic waves I: flood movement in long rivers. II: a theory of traffic flow on long crowded roads. Proceedings Royal So- ciety,Series A,Mathematical and Physical Sciences, London . 1955 被引量:1
  • 5N.A. Derzko,A. J. Ugge,E. R. Case.Evaluation of dy- namic freeway flow model by using field data. Trans- portation Research Record . 1983 被引量:1
  • 6C.F. Daganzo.In traffic flow,cellular automata = kine- matic waves. Transportation Research . 2006 被引量:1
  • 7L.J. Norman.The legacy and future of CFD at Los Ala- mos. Canadian ‘‘‘‘96 CFD Conference . 1996 被引量:1
  • 8Professor Spalding‘‘‘‘s biography. http://www.ham.co. uk/website/new/dbs.htm . 2007 被引量:1
  • 9J.E. Berlamont,K. Trouw,G. Luychx.Shear stress dis- tribution in partially filled pipes. Journal of Hydraulic Engineering ASCE . 2003 被引量:1
  • 10K. Chung,J. Rudjanakanoknad,M. J. Cassidy.Relation between traffic density and capacity drop at three free- way bottlenecks. Transportation Research . 2007 被引量:1

共引文献6

同被引文献112

引证文献17

二级引证文献38

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部