围压对TBM滚刀破岩影响规律的线性切割试验研究 被引量:26

Linear cutting tests on effect of confining stress on rock fragmentation by TBM cutter
原文传递
导出
摘要 随着TBM技术在深埋隧道工程领域的应用及发展,TBM开挖过程中由高埋深或各向异性引起的岩石应力问题越来越受到人们的重视。应用北京工业大学自行研制的大型机械破岩试验平台,对4组双向等围压水平下(0,5,10和15 MPa)的大尺寸(1.0 m×1.0 m×0.6 m)北山花岗岩岩样进行线性切割试验,研究不同围压条件下滚刀破岩时作用力的曲线特征,分析围压对滚刀法向力、滚动力、岩体特征掘进指数、破岩岩片厚度和破岩比能的影响效应,并探讨围压对TBM现场掘进速率的影响。研究结果可为不同地应力条件下TBM开挖时刀盘动力参数设计与施工运行参数优化提供参考。 In deep tunnel construction,TBM faces the rock stress problems induced by overburden or anisotropic stress,which had been under more and more attention. In this paper,full-scale cutting tests are presented to investigate the effect of different confining stresses,i.e. 0,5,10,and 15 MPa,on rock fragmentation of large intact granite sample with dimension of 1.0 m×1.0 m×0.6 m induced by TBM cutter. In these tests,the characteristics of force-time curves,normal forces,rolling forces,specific rock mass boreability index,chipping thickness and specific energy affected by confining stress were analyzed.
出处 《岩石力学与工程学报》 EI CAS CSCD 北大核心 2016年第2期346-355,共10页 Chinese Journal of Rock Mechanics and Engineering
基金 国家自然科学基金资助项目(51308196) 国防科技重点项目(科工二司[2012]492号) 国家重点基础研究发展计划(973)项目(2014CB04690x)~~
关键词 隧道工程 全断面掘进机 围压 花岗岩 全尺寸线性切割试验 掘进速率 tunnelling engineering tunnel boring machine(TBM) confining stress granite full-scale linear cutting tests penetration rate
  • 相关文献

参考文献23

  • 1REHBOCK-SANDER M, BOISSONNAS Y. Gotthard base tunnel special aspects and state of the works[C]// Proceedings of the ITA 2005, Underground Space Use: Analysis of the Past and Lessons for the Future. London: [s.n.], 2005:485 - 490. 被引量:1
  • 2GONG Q M, YIN L J, WU S Y, et al. Rock burst and slabbing failure and its influence on TBM excavation at headrace tunnels in Jinping II hydropower station[J]. Engineering Geology, 2012, 124(1): 98 - 108. 被引量:1
  • 3Zhang Jingjian(North China Institute of Water Conservancy and Hydroelectric Prower, Zhengzhou 450045).TBM的应用及其有关问题和展望[J].岩石力学与工程学报,1999,18(3):363-367. 被引量:85
  • 4BORDET C, COMES CL Etude prrvisionnelle de la roches au tunneller[J]. Tunnels et Ouvrages Souterrains forabilit6 des 1975, (7): 11 - 17.(in French). 被引量:1
  • 5GEHRING K. Design criteria for TBM's with respect to real rock pressure[C]// Proceedings of Tunnel Boring Machines: Trends in Design and Construction of Mechanized Tunneling. Hagemberg[s.n.], 1995:43 - 53. 被引量:1
  • 6TARKOY P J, MARCONI M. Difficult rock combination and associated geological conditions[C]//Proceedings of the 6th Congress Tunnelling 91. London: [s.n.], 1991:195 - 207. 被引量:1
  • 7KLEIN S, SCHMOLL M, AVREY T. TBM performance at four hard rock tunnels in California[C]//Proceedings of R.ETC. San Francisco: [s.n.], 1995.. 61-65. 被引量:1
  • 8龚秋明,佘祺锐,侯哲生,姜厚停,彭琦.高地应力作用下大理岩岩体的TBM掘进试验研究[J].岩石力学与工程学报,2010,29(12):2522-2532. 被引量:32
  • 9吴世勇,龚秋明,王鸽,侯哲生,佘祺锐.锦屏Ⅱ级水电站深部大理岩板裂化破坏试验研究及其对TBM开挖的影响[J].岩石力学与工程学报,2010,29(6):1089-1095. 被引量:43
  • 10HUANG H, DAMJANAL B, DETOURNAY E. Normal wedge indentation in rocks with lateral confinement[J]. Rock Mechanics and Rock Engineering, 1998, 31(2): 81 - 94. 被引量:1

二级参考文献60

  • 1吴世勇,任旭华,陈祥荣,张继勋.锦屏二级水电站引水隧洞围岩稳定分析及支护设计[J].岩石力学与工程学报,2005,24(20):3777-3782. 被引量:59
  • 2张黎明,王在泉,贺俊征,任禀洁.卸荷条件下岩爆机理的试验研究[J].岩石力学与工程学报,2005,24(A01):4769-4773. 被引量:21
  • 3张厚美,吴秀国,曾伟华.土压平衡式盾构掘进试验及掘进数学模型研究[J].岩石力学与工程学报,2005,24(A02):5762-5766. 被引量:75
  • 4和佐勇次郎.日本盾构施工法之现状[J].土木技术,1991,(10):56-64. 被引量:2
  • 5傅冰俊.国际地下工程发展动向[J].岩石力学与工程动态,1996,(2):3-4. 被引量:3
  • 6张镜剑.地下雷达及其在岩土工程中的初步应用.河南省岩石力学与工程学会第八次学术研讨会论文集[M].郑州,1996.. 被引量:1
  • 7中国水利水电长江葛洲坝工程局(译).海峡隧道[M].,.. 被引量:1
  • 8DOWDING C H,ANDERSSON C A.Potential for rock bursting and slabbing in deep caverns[J].Engineering Geology,1986,22(3):265-279. 被引量:1
  • 9KAISER P F.Failure mechanisms and rock support aspects-the international consultation report for the key technology of safe and rapid construction for Jinping II Hydropower Station high overburden and long tunnels[R].[S.l.]:[s.n.],2009. 被引量:1
  • 10DIEDERICHS M S.The 2003 Canadian geotechnical colloquium:mechanistic interpretation and practical application of damage and spalling prediction criteria for deep tunnel[J].Canadian Geotechnical Journal,2007,44(9):1 082-1 116. 被引量:1

共引文献210

同被引文献249

引证文献26

二级引证文献137

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部