350MW超临界间接空冷汽轮机组调试过程中出现的问题及处理 被引量:2

Treatment and Problems Encountered in Unit Debugging of 350 MW Supercritical Indirect Air Cooling Steam Turbine
原文传递
导出
摘要 汽轮机的整套启动调试、小汽轮机系统调试是汽轮发电机组调试的重要组成部分。本研究对A电厂三期2×350 MW超临界间接空冷汽轮机组汽轮机的整套启动调试、小汽轮机系统调试过程和试运行期间出现的问题进行了详细的介绍,阐述了分析处理过程,总结了调试经验和运行经验。 The entire turbine start-up debugging,debugging of small turbine system is an important part of steam turbine generator unit commission. The research has a detailed introduction on the problems encountered in the commission process and debugging of small turbine system of the three 2 × 350 MW supercritical indirect air cooling steam turbine in A power plant. And it describes the process of treatment analysis and sums up the debugging experience and operational experience.
作者 张士龙
出处 《热能动力工程》 CAS CSCD 北大核心 2015年第5期813-815,832,共3页 Journal of Engineering for Thermal Energy and Power
关键词 超临界汽轮机组 启动调试 系统调试 Supercritical Turbine,package start-up debugging of steam turbine,small turbine system debugging
  • 相关文献

参考文献2

  • 1张士龙.新疆华电喀什热电有限责任公司5号机组汽机专业整套启动调试报告[R].华电电力科学研究院,2014. 被引量:1
  • 2GB_T_8117-1-2008汽轮机热力性能试验规程[s].中华人民共和国国家质量监督检验检疫总局,中国国家标准化管理委员会,2008. 被引量:1

同被引文献9

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部