摘要
简述了湿法脱硫产生的脱硫废水的特点及其化学混凝沉淀法处理工艺,针对废水的特点进行工程设计,给出了废水处理系统、污泥脱水系统和加药系统的具体的设计参数和尺寸。同时结合调试过程中出现的问题,对工艺系统提出了完善建议。
Characteristics of wet desulfurization wastewater of heat-engine plant and process of coagulation precipitate were briefly introduced. Engineer was designed with characteristics of wet desulfurization wastewater. The specific design parameters and size of wastewater treatment system and sludge dewatering system and adding medicine system were given. According with problems appeared in preliminary test, suggestions of process system were offered.
出处
《广东化工》
CAS
2014年第14期203-204,共2页
Guangdong Chemical Industry
关键词
脱硫废水
湿法脱硫
工程设计
废水处理站
desulfurizationwastewater
wetdesulfurization
engineering design
wastewater disposal plant