摘要
选取工序工时、工序成本、工序质量作为基本变量,利用蒙特卡洛模拟和网络不交化方法构建了一种网络图项目多目标(工期、成本、质量)可靠性优化模型。从数理统计的角度,计算工期可靠性、成本可靠性、质量可靠性、项目施工可靠性及定义工序影响度,对优化其目标可靠性指明方向。通过对某工程项目进行实证研究,验证了该可靠性模型的可行性与实用性,为评价网络图项目提供了一种有力的工具。
Activity time, activity cost, activity quality are selected as basic variables, a project reliable and optimized model of multi-objective(project duration, project cost, project quality)in network diagram is established by Monte Carlo simu-lation and network disjointed method. From the perspective of mathematical statistics, project duration reliability, project cost reliability and project quality reliability, project construction reliability are calculated, and activity’s influence degree is defined, indicating the direction to optimize the target reliability. The feasibility and practicability of the reliable model has been proved by empirical research of one project, providing a powerful tool for assessing network diagram project.
出处
《计算机工程与应用》
CSCD
2014年第1期218-221,共4页
Computer Engineering and Applications
基金
国家自然基金(No.50878185)
成都铁路局项目(No.CX11062)
关键词
蒙特卡洛模拟
网络不交化法
数理统计
工序影响度
项目工期可靠性
项目成本可靠性
项目质量可靠性
项目施工可靠性
Monte Carlo simulation
network disjointed method
mathematical statistics
activity’s influence degree
project duration reliability
project cost reliability
project quality reliability
project construction reliability