针对山东埠村煤矿911采区开采条件,提出了利用高水材料充填方法对承压含水层上已经开采的条带煤柱进行二次置换开采的技术思路。从充填体稳定性以及置换充填开采对底板破坏的影响等方面分析了其技术可行性,确定了采区高水材料充填置换开采承压水上条带煤柱的合理方案,即首先对条带老采空区(平均采宽15 m)进行充填,待其充填体强度达2.2 MPa后对条带煤柱(平均留宽20 m)进行回收,回收过程中每间隔一个条带煤柱进行一次充填,该方案共需要充填体体积占采区采出煤层体积的65.6%。
According to the mining condition of 911 mining area of Bucun Coal Mine,a technical scheme of replacement mining strip coal pillars above confined water using high water material was proposed.From the point of backfill stability and replacement mining influence on floor destruction,technical feasibility was analyzed and a rational solution to the pillar replacement was proposed.The primary backfill of the strip mined-out area with an average width of 15 m was conducted,followed by the 20 m width pillar extraction with the backfill of every other pillar.The volume of backfill accounts for 65.6% of the coal in all the mining area.
出处
《煤炭学报》
EI
CAS
CSCD
北大核心
2011年第6期909-913,共5页
Journal of China Coal Society
基金
国家重点基础研究发展计划(973)资助项目(2007CB209403)
关键词
高水材料
承压含水层
条带开采
充填开采
绿色开采
high water material
confined aquifer
strip mining
filling mining