钢衬和钢筋混凝土联合承载蜗壳结构分析 被引量:7

Analysis for composite structure of steel scroll case and outer covering reinfoced concrete
下载PDF
导出
摘要 对某巨型钢衬钢筋混凝土联合承载蜗壳,采用三维非线性有限元法计算结果表明:当弹性垫层6cm和垫层材料弹模为2MPa时,原设计的钢衬为6cm偏厚,钢衬与座环连接部位应力集中较大;给出了随内水压力增加,埚壳外包混凝土塑性变形和开裂区的发展过程。对上述问题提出了改进措施建议。 The three dimensional nonliear element method is used to calculate compositestructure stress of huge steel scroll case and outer covering reinforced concrete.The result ofcalculating indicates:When the thickness of elastic pad is 6 cm and its elastic modulus is 2-20MPa,the max.stress of steel scroll case is smaller than project strength.It is suggested that thethickness of steel scroll case be reduced or the low strength steel material be selected.
出处 《大连理工大学学报》 CAS CSCD 北大核心 1995年第3期389-394,共6页 Journal of Dalian University of Technology
基金 中国电力部规划设计院1990~1992前期工程基金
关键词 蜗壳 结构分析 钢筋混凝土 联合承载 钢衬 spiral casings structural analysis steel plates reinforced concrete/bearing jointly
  • 相关文献

参考文献6

  • 1周力,压力管道学术讨论会,1992年 被引量:1
  • 2王树人,水电站建筑物(第2版),1992年 被引量:1
  • 3张玉美,1990年 被引量:1
  • 4张义林,第二届全国水电站压力管道学术讨论会论文专集,1990年 被引量:1
  • 5张进平,水利水电科学研究院科学研究论文集.19,1984年 被引量:1
  • 6庄万康,水电建设参考资料,1982年,2卷,10页 被引量:1

同被引文献100

引证文献7

二级引证文献77

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部