期刊文献+

秦山核电站汽轮发电机组首次冲转试验的技术特色 被引量:3

Technical Features of First Initial Runup of The Turbine-Generator Set in Qinshan Nuclear Power Plant
下载PDF
导出
摘要 秦山核电站于1991年3月29日利用非核蒸汽首次冲转汽轮发电机组到额定转速3000r/min.这次机组冲转的汽源是利用一回路主泵转动时机械能转化为热能而产生的蒸汽.冲转成功不仅可免除另行设置调试锅炉,而且还实现了一、二回路的联动试车,这是本次试验的技术特色.本文概述用非核蒸汽冲转汽轮发电机组的技术准备、试验情况及结果. On March 29th, 1993, the Qinshan NPP succeeded in the initial runup of the turbine-generator set up to the rated 3000r/min by utilizing non-nuclear steam. The steam supply to the initial runup was taken from steam produced from energy conversion from mechnical to thermal while the reactor coolant pump was operating. The success of the test showed that not only no commissioning boiler needs to be installed for this special purpose, but also combined-runup of the primary with secondary circuit is realized. These are technical features of this test. In the paper is presented technical preparation, testing and results of this test. Figs 6.
出处 《动力工程》 CSCD 1993年第5期1-8,共8页 Power Engineering
  • 相关文献

同被引文献26

引证文献3

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部