阐述讨论了我国首台650MW核电机组(秦山二期1号汽轮发电机组)非核蒸汽冲转试验的目的、冲转方案的选择、汽源能力及冲转所需蒸汽量的估算,并对非核蒸汽冲转的具体实施情况、试验结果及发现的主要问题进行了分析研究。
This paper expatiated and discussed that the main purpose, the scheme, estimation of steam supply capability and the availability of initial startup of Qinshan II 650MW nuclear unit with non-nuclear steam. This paper also Analyzed the test result and main issue and bringed forward cognition and experience.
出处
《汽轮机技术》
北大核心
2005年第2期142-144,146,共4页
Turbine Technology
关键词
非核蒸汽
冲转
汽轮发电机组
turbo-generator unit
non-nuclear steam
strat-up