原矿仓垮塌后的修复方法研究 被引量:1

Study on the reinforcement method after the collapse of the ore bin
下载PDF
导出
摘要 原矿仓是金属矿山最为重要的工程,是矿岩集贮与转动的咽喉工程。原矿仓的稳定和安全对矿山的正常生产影响极大,其破坏不但影响生产,修复难度极大,而且威胁整个系统的安全。以三山岛金矿新立矿区1号原矿仓为背景,对发生垮塌的因素进行了分析和说明,并就相关问题提出了1号原矿仓的修复治理技术方案。 The crude ore bin is the most important project of metal mine.It is the vital engineering for the reservoir and the rotation of ore.The stability and safety of the crude ore bin have great influence on the normal production of mine.The damage affects production and it is a big challenge for repair.Furthermore,the damage threatens the safety of the whole system.An example is the No.1 crude ore bin in Xin Li mining area of Sanshandao.The author analyzed and explained the factors that led to the collapse and put forward the technical plans for repairing and management of the mine.
作者 王平
出处 《中国矿业》 北大核心 2017年第S2期135-137,146,共4页 China Mining Magazine
关键词 原矿仓 垮塌 修复 破坏原因 ore bin collapse repair failure reason
  • 相关文献

参考文献4

二级参考文献7

共引文献41

同被引文献3

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部