沙坪煤矿按照年度工作计划在2012年2月中旬对18204综采工作面末采回撤工作进行了施工,以"安全、优质、快速、低耗"为工作目标,紧紧围绕着安全措施到位、技术指导到位、跟班组织到位、安全监督到位进行施工,并且按照计划圆满完成回撤工作。下面就18204综采工作面末采及回撤工作进行分析。
Shaping Coal Mine carried out construction work on the end of the 18204 fully mechanized mining face in midFebruary 2012 in accordance with the annual work plan,with the goal of'safety,high quality,fast and low consumption',closely surrounded the construction principal of'proper safety measures,proper technical guidance,proper follow-up organization,proper safety supervision',the retracement work was successfully completed according to the plan.The paper introduced the end mining and retracement work of 18204 fully mechanized mining face in detail.