摘要
新建咸宁货场综合物流基地工程选址于王家祠水库下游,一旦水库发生溃坝,将对铁路货场的运营安全构成极大威胁。铁路勘测阶段通过详细调查水库情况,结合铁路工程水文勘测设计规范,研究了上游水库对新建货场选址处流量的影响,为货场的选址和设计提供了重要参考,相关研究思路可为类似铁路工程的勘察设计提供借鉴。
The newly-built Xianning freight yard comprehensive logistics base engineering is located in the downstream of Wangjiaci reservoir.Once the dam breaks,it will pose a great threat to the operation safety of railway freight yard.In the stage of railway survey,the influence of upstream reservoir on the flow at the site of new freight yard is studied by investigating the reservoir situation in detail and combining with the hydrological survey and design specifications of railway engineering,which provides an important reference for the site selection and design of freight yard.The relevant research ideas can provide reference for the survey and design of similar railway engineering.
作者
张记东
ZHANG Jidong(China Railway Fifth Survey and Design Institute Group Co.,Ltd.,Beijing 102600,China)
出处
《工程技术研究》
2024年第2期52-54,共3页
Engineering and Technological Research
关键词
上游水库溃坝
铁路货场
勘测设计
溃坝流量
upstream reservoir dam break
railway freight yard
survey and design
dam break flow