摘要 郑州市某新建污水处理厂总规模为10×10^(4)m^(3)/d,采用全地下式布置,出水COD需达到《地表水环境质量标准》(GB 3838—2002)的Ⅲ类标准,即COD≤20 mg/L。该厂采用两级活性焦吸附作为深度处理工艺。该案例两级活性焦吸附池和活性焦房的平面布置、设计参数、操作时序等设计经验,可为其他类似工程提供参考。 The total scale of a new wastewater treatment plant(WWTP)in Zhengzhou is 10×10^(4) m^(3)/d,and it is all-underground.The effluent COD should meet level Ⅲ of Environmental Quality Standards for Surface Water(GB 3838-2002),that is,COD≤20 mg/L.Two-stage activated coke adsorption is used as advanced treatment unit in the WWTP.The layout,design parameters,operation sequence of the two-stage activated coke adsorption tank and chamber are elaborated,which can provide reference for other similar projects.
作者 张永森 李国金 刘振 艾可 ZHANG Yong-sen;LI Guo-jin;LIU Zhen;AI Ke(Tianjin Municipal Engineering Design&Research Institute Co.Ltd.,Tianjin 300392,China;Tianjin Key Laboratory of Infrastructure Durability,Tianjin 300392,China;Hangzhou Huishui Technology Co.Ltd.,Hangzhou 310051,China)
出处 《中国给水排水》 CAS CSCD 北大核心 2023年第14期120-123,共4页 China Water & Wastewater
关键词 全地下污水处理厂 深度处理 活性焦 两级吸附 all-underground wastewater treatment plant advanced treatment activated coke two-stage adsorption
  • 相关文献

参考文献5

二级参考文献36

共引文献42

同被引文献17

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部