摘要
通过对京广高铁接触网弹性吊索磨损问题进行分析,研究问题类型和成因,制定合理整治方案,整治后的设备满足动车组高速运行条件,为高速铁路弹性吊索状态检查及调整维护提供参考。
On the basis of analyzing the problems of wear of OCS stitch wires of Beijing-Guangzhou high-speed railway,studies are made on the causes and types of the problems,and reasonable renovation schemes are established.The renovated equipment meets the requirements of high-speed running conditions of EMU,providing references for inspection of status,adjustment and maintenance of stitch wires of high-speed railway.
出处
《电气化铁道》
2023年第S01期137-140,共4页
Electric Railway
关键词
接触网
弹性吊索
调整
检查
OCS
stitch wire
adjustment
inspection