期刊文献+

影响工艺水汽提塔长周期运行的原因分析及对策

ANALYSIS OF FACTORS AFFECTING LONG-CYCLE OPERATION OF PROCESS WATER STRIPPING TOWER AND THE COUNTERMEASURES
下载PDF
导出
摘要 主要针对中国石油独山子石化分公司220 kt/a乙烯装置,工艺水汽提塔发生聚合物堵塞问题,严重影响该塔的长周期平稳运行。经分析原因,采取优化工艺操作,增加工艺水阻垢剂,来降低水中油含量和抑制聚合物生成,从而达到和改善工艺水汽提塔的水质,减少由于聚合物堵塞问题引起装置停车的风险,为乙烯装置急冷系统长、满、优运行奠定了坚实的基础。 The polymer blockage in the process water stripping tower of the 220 kt/a ethylene plant at PetroChina Dushanzi Petrochemical Company serious affected the long-cycle and stable operation of the tower.By analyzing the reasons,the process operation was optimized and process water scale inhibitor was added to reduce the oil content of water and inhibit the formation of polymer,so as to improve the water quality of process water stripping tower and reduce the risk of plant shutdown caused by polymer blockage,laying a solid foundation for the long-cycle and optimal operation of the quench system of ethylene plant at full load.
作者 王俊斌 王军伟 王金柱 马俊 吕小刚 Wang Junbin;Wang Junwei;Wang Jinzhu;Ma Jun;Lyu Xiaogang(PetroChina Dushanzi Petrochemical Company,Dushanzi,Xinjiang,P.C.833699)
出处 《乙烯工业》 CAS 2023年第1期28-31,37,I0001,共6页 Ethylene Industry
关键词 工艺水 乳化反应 聚合物堵塞 优化措施 process water emulsion reaction polymer blockage optimization measure
  • 相关文献

参考文献1

二级参考文献3

共引文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部