成渝高铁内江北站提质改造站场过渡方案研究

Study on Transition Scheme of Neijiang North Station of Chengdu Chongqing High Speed Railway
下载PDF
导出
摘要 既有线改建项目中施工过渡方案是站场改建施工顺利进行和完成的关键。根据内江北站的具体情况,对站场改建及过渡施工方案进行了研究,并对方案进行了优化。研究结果表明该方案能为内江北站工程提质达速提供可靠的依据。 In the existing line reconstruction project,the construction transition scheme is the key to the smooth progress and completion of station reconstruction.According to the specific situation of Neijiang North Station,this paper studies the station reconstruction and transition construction scheme,and optimizes the scheme.The research results show that the scheme can provide a reliable basis for the speed and quality improvement project of Neijiang North Station.
作者 赵亚辰 ZHAO Yachen(China Railway Eryuan Engineering Group Co.,Ltd,Chengdu,Sichuan 610031)
出处 《现代工程科技》 2022年第1期27-30,共4页 Modern Engineering Technology
关键词 施工过渡 站场改建 内江北站 优化 construction transition station reconstruction Neijiang North Station optimization
  • 相关文献

参考文献8

二级参考文献4

共引文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部