深水桥梁大型基础施工方案比选研究 被引量:2

Study on Comparison and Selection of arge-scale Foundation Construction Schemes for Deep-water Bridges
下载PDF
导出
摘要 依托某跨河桥梁深水基础施工,针对该桥址处复杂的地质、气候及水文条件,对双壁钢围堰、放坡开挖双壁钢围堰、锁扣钢管桩围堰3种方案的结构构造、围堰布置型式、施工方法及其优缺点展开研究,并从工期、成本、安全风险、技术风险等方面进行综合比选,最终从成本和可行性方面考量,认为3种方案中,放坡开挖双壁钢围堰方案最优。 Relying on a deep-water foundation construction of river-crossing bridge,in view of the bridge in the complex geology,climate and hydrological conditions,the structure constructions,cofferdam arrangement types,construction methods,advantages and disadvantages of three schemes of double-wall steel cofferdam,double-wall steel cofferdam by slope excavation and locking steel pipe pile cofferdam structure are studied.And the comprehensive comparison is carried out from the aspects of construction period,cost,safety risk and technological risk.Finally by considering the cost and the feasibility,the scheme of double-wall steel cofferdam by slope excavation is the best in three schemes.
作者 王军舰 刘均儒 WANG Junjian;LIU Junru
出处 《城市道桥与防洪》 2021年第11期130-133,M0013,共5页 Urban Roads Bridges & Flood Control
关键词 深水 基础 双壁钢围堰 锁扣钢管桩围堰 deep water foundation double-wall steel cofferdam locking steel pipe pile cofferdam
  • 相关文献

参考文献5

二级参考文献30

共引文献64

同被引文献11

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部