煤矿井下岩溶黄泥带快速掘进技术应用实践 被引量:1

Application practice of rapid excavation technology in Karst yellow mud belt in underground coal mine
下载PDF
导出
摘要 在煤矿井下巷道掘进过程中,复杂的地质构造,对单进水平起着很大制约作用,也给施工过程中的安全管理带来极大困难。重庆三圣实业股份有限公司八仙洞煤矿+435 m主平硐,以石门形式布置,先后穿过须家河组(T3xj)→雷口坡组(T2l)→嘉陵江组(T1j),在掘进至嘉陵江组第三亚段(T1j4-3)时,多次揭露岩溶黄泥带地质构造,严重制约单进水平、影响安全施工。通过多次实践摸索,总结出了采用“素喷、带帽点柱、超前管棚+格栅支架”3种临时支护配合11号矿工字钢支架作为永久支护的方式安全顺利通过了岩溶黄泥区域,巷道掘进速度较砼碹支护提高3倍。 in the process of underground roadway excavation in coal mine,the complex geological structure has a great restricting effect on the single level,and also brings great difficulties to the safety management in the construction process.The+435 m main adit of baxiandong coal mine of Chongqing Sansheng Industrial Co.,Ltd.is arranged in the form of crosscut,which successively passes through Xujiahe Formation(t3xj)→Leikoupo Formation(T2L)→Jialingjiang formation(T1j).When driving to the third sub section of Jialingjiang formation(t1j4-3),the geological structure of karst yellow mud zone is repeatedly exposed,which seriously restricts the single level and affects the safety of construction.Through many times of practice and exploration,three kinds of temporary support,namely"plain shotcreting,capped point pillar,advanced pipe shed+grid support",combined with 11#miner's steel support,are summarized to pass through the karst yellow mud area safely and smoothly,and the driving speed of roadway is three times higher than that of concrete arch support.
作者 邓文平 DENG Wenping(Chongqing Sansheng Industrial Co.,Ltd.,Chongqing401320,China)
出处 《煤矿现代化》 2021年第6期26-28,31,共4页 Coal Mine Modernization
关键词 岩溶黄泥 快速掘进 临时支护 永久支护 Karst yellow mud rapid excavation temporary support permanent support
  • 相关文献

参考文献3

二级参考文献34

共引文献720

同被引文献1

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部