结合某国际大型水电工程项目,对业主指定料场因覆盖层地质条件发生变化引起的料场争议进行了分析介绍。承包商通过对招标文件技术合同条件充分理解和对指定料场地质条件的预判,有针对性的编制施工技术方案,地质补勘,备用料场选择与勘探,不同料源骨料对比,聘请国际知名专家评估等途径,在与工程师料场争议博弈中取得完胜,最终工程师颁发了料场变更令,承包商获得了费用和工期补偿,规避了成本和工期风险,案例经验可供类似工程参考。
A contract dispute case in a large-scale international hydropower project is analyzed,in which the geological conditions of the overburden of the owner-designated borrow area are changed.Based on the full understanding of the technical contract conditions of the bidding documents and the prediction of the geological conditions of the designated borrow area,the contractor took various measures,including the preparation of construction technical schemes,supplementary geological exploration,exploration and selection of alternate borrow area,comparison of aggregates from different sources,and evaluation by internationally renowned experts.With the support of these measures,the contractor won the dispute completely.Finally,the engineer issued the borrow change order.The contractor got the construction cost and duration compensation and avoided the risks.The case is a useful reference for similar projects.
作者
石砾
SHI Li(China Gezhouba Group Overseas Investment Co., Ltd., Beijing 100025, China)
出处
《水电与新能源》
2021年第9期8-10,28,共4页
Hydropower and New Energy
关键词
料场开采
覆盖层
勘探
开挖边界
料场变更
material excavation
overburden
exploration
excavation boundary
change of the borrow area