摘要
GIS安装是海上升压站建造安装的一个重要环节。海上升压站上部组块采用分片预制、空间组对一体化建造方法。论文分析传统GIS安装方法在施工中存在的缺点,提出优化改进的海上升压站GIS深度预制施工技术,介绍了该技术流程,并结合工程实例进行了效果分析。实践证明,此方法与传统安装方法相比具有明显优势,对今后海上风电项目中GIS的安装有一定的参考意义。
The installation of GIS is an important link in the construction and installation of offshore booster stations.As the upper blocks of offshore booster stations are built by the method of prefabrication in pieces and integration of space groups.This paper analyzes the disadvantages of traditional GIS installation method in construction,puts forward the optimized and improved construction technology of GIS depth prefabrication for offshore booster station,introduces the technical process,and analyzes the effect with the engineering example.The practice proves that this method has obvious advantages compared with the traditional installation method,and it has certain reference significance for the installation of GIS in offshore wind power projects in the future.
作者
常凌凌
CHANG Ling-ling(CNPC Offshore Engineering Company Limited,Qingdao 266000,China)
出处
《工程建设与设计》
2021年第15期44-46,63,共4页
Construction & Design for Engineering
关键词
海上升压站
GIS安装
优化改进
效果分析
offshore booster station
GIS installation
optimization and improvement
effect analysis