摘要
随着GIS变电站的推广应用,GIS组合电器增容也随之增多,如何在现场满足GIS安装环境要求,提高组合电器安装质量,值得研究。以220 kV GIS组合电器母线延伸、间隔增容为例,阐述了GIS组合电器的现场安装要点、工艺要求、安装步骤及现场试验,设计了组合电器现场安装工作室,为GIS组合电器扩建增容提供了参考。
With the popularization and application of GIS equipment in substation, the cases of capacity enlargement of GIS composite apparatus also increased. How to meet the requirements of GIS installation environment on site and improve the installation quality is worthy to be studied. This paper,taking the busbar extension and interval expansion of 220 kV GIS composite apparatus as an example,elaborates the installation points,the technological requirements,the installation steps and field test. Besides,the workshop for composite apparatus installing is designed,which could provide a reference for GIS composite apparatus expansion.
出处
《山西电力》
2014年第4期9-11,共3页
Shanxi Electric Power
关键词
GIS
组合电器工作室
安装工艺
现场试验
GIS
composite apparatus workshop
the installation process
field test