缩短配电网带电作业现场工作时间的研究 被引量:2

Research on Live Working Time in Shortening Electrification of Distribution Network Working Duration
下载PDF
导出
摘要 针对大连自贸区配电网带电作业现场工作时间超时的问题,采用PDCA循环,结合5W1H等方法分析原因,制定对策并进行现场实施。对优化措施进行巩固和推广,不仅缩短了工作时间,创造了极大的经济效益,而且提高了供电可靠率,为大连自贸区建设提供保障。 Aiming at the long working time of live operation in electrification of distribution network in Dalian free trade zone,it uses PDCA cycle combining with 5W1H and so on methods to analyze reasons.It formulates countermeasures and implements them on site.Consolidating and popularizing the optimization measures not only shorten the working time,create great economic benefits,but also improve the reliability of power supply to provide guarantee for the construction of Dalian free trade zone.
作者 吴红雨 何双 刘振宇 张浩然 苗雨 WU Hongyu;HE Shuang;LIU Zhenyu;ZHANG Haoran;MIAO Yu(State Grid Dalian Power Supply Company,Dalian,Liaoing 116011,China)
出处 《东北电力技术》 2021年第3期16-19,共4页 Northeast Electric Power Technology
关键词 配电网带电 PDCA 时间 electrification of distribution network PDCA time
  • 相关文献

参考文献9

二级参考文献36

共引文献260

同被引文献19

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部