桥梁工程建设中的悬臂现浇梁挂篮法施工技术 被引量:1

Construction technology of cantilever cast-in-place beam hanging basket method in bridge engineering construction
下载PDF
导出
摘要 结合桥梁工程实例,围绕悬臂现浇挂篮法展开探讨,具体包含总体施工工序、挂篮安装、混凝土浇筑、挠度控制要点等多个方面,最后对挂篮法的施工效果加以总结,从而提高悬臂现浇挂篮施工水平。 Combined with the bridge engineering example, the discussion was carried out around the cantilever cast-in-place basket method, including the overall construction process, hanging basket installation, concrete pouring, and deflection control points. Finally, the construction effect of the cantilever method was summarized to improve the cantilever construction level of cast-in-place hanging basket.
作者 严斌 YAN Bin(China Communications 2nd Navigational Bureau 2nd Engineering Co.,Ltd,Chongqing 401120,China)
出处 《中国高新科技》 2020年第20期143-144,共2页
关键词 桥梁工程 悬臂现浇箱梁 挂篮法 bridge engineering cast-in.place box girder hanging basket method