武汉雷神山医院建设配套齐全、专业多、标准高,需10d内快速完成建设,项目采取全专业穿插施工,通过梳理施工工序、合理组织,最终形成水平以平面分区穿插、竖向以工艺衔接穿插的三维立体全专业穿插模式,最终实现全专业穿插,为雷神山医院顺利移交打下基础。梳理整个建设过程中的施工工序,探讨全专业穿插在应急传染病医院建设中的相应流程及注意要点。
The construction of Wuhan Leishenshan hospital is complete,professional and high standard.It needs to be completed within 10 days.The project adopts full professional interspersed construction,by combing the construction process and reasonable organization,finally,a three-dimensional professional interpenetration mode is formed,which is horizontal interpenetration by plan partition and vertical interpenetration by process connection,the whole specialty will be interspersed.The foundation is laied for the smooth handover.This paper sorts out the construction process in the whole construction process,and discusses the corresponding process and the key points in the all professional of emergency infectious disease hospital.
作者
庞海枫
黄飞
尚乐乐
王远航
方翔
PANG Haifeng;HUANG Fei;SHANG Lele;WANG Yuanhang;FANG Xiang(China Construction Third Bureau First Engineering Co.,Itd,Wuhan,Hubei 430040,China)
出处
《施工技术》
CAS
2020年第12期114-116,共3页
Construction Technology
基金
中建三局2020年度科技研发课题(CSCEC3B-2020-28):应急呼吸道传染病医院快速建造技术与总承包管理。
关键词
医院
全专业
工序
施工技术
hospitals
all professional
process
construction