辛置矿大采高工作面覆岩运移及超前支承应力分布规律研究 被引量:2

Study on the moving rock law and the distribution of advanced support stress in large mining depth working face of Xinzhi Mine
下载PDF
导出
摘要 为掌握辛置煤矿2号煤层大采高工作面回采作业应力分布及覆岩运动规律,具体分析工作面覆岩三带及超前支承压力分布规律,采用理论、模拟与实测相结合的手段,对超前支承压力分布进行现场实测分析。结果表明,大采高工作面覆岩垮落带、裂隙带的发育高度分别在17~25 m和30~35 m,工作面超前支承压力的范围为50 m。 In order to master the stress distribution and overburden movement law during the mining operation of the No. 2 coal seam in Xinzhi Coal Mine, the distribution law of overburden zones and advanced bearing pressures in the working face were specifically analyzed. The overburden zones were distributed using theory, simulation and actual measurement. The pressure distribution of the advanced support was specifically analyzed using on-site measured analysis methods. The results showed that the development heights of the overburden collapse zone and fracture zone in the large mining depth working face were in the range of 17 ~ 25 m and 30 ~ 35 m respectively;the range of advanced bearing pressure in the working face was 50 m.
作者 郑田野 Zheng Tianye(Xinzhi Mine,Huozhou Coal and Electricity Group,Huozhou 031412,China)
出处 《煤炭与化工》 CAS 2020年第6期5-8,共4页 Coal and Chemical Industry
关键词 大采高 钻孔应力计 超前支承压力 large mining height drilling stress gauge advanced support pressure
  • 相关文献

参考文献6

二级参考文献14

共引文献29

同被引文献12

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部