摘要
吉林蛟河抽水蓄能电站,地下系统施工通道布置优先利用交通洞、通风洞等永久洞室,在此基础上结合枢纽布置、工程特点、地形地质条件、施工进度等,增设地下系统施工支洞,以满足工程地下洞室施工交通要求。在施工通道尺寸确定时,既满足了出渣、混凝土运输等施工要求,也兼顾了重大件设备运输要求。
Jiaohe pumped-storage power station in Jilin, the underground system construction access layout is priority to using traffic tunnel, ventilation tunnel and other permanent caverns, and in combination with the hub layout, project characteristics, topographic and geological conditions, construction schedule, etc., the underground system construction branches are added to meet the construction traffic requirements of underground caverns.When the construction channel size is determined, it can meet the transportation needs of slag and concrete as well as the transportation requirements of major equipment.The design of this project can provide reference for other similar projects.
作者
王富强
王福运
冯吉新
WANG Fu-qiang;WANG Fu-yun;FENG Ji-xin
出处
《东北水利水电》
2020年第2期4-7,71,共5页
Water Resources & Hydropower of Northeast China
关键词
抽水蓄能电站
地下系统
施工通道
布置
pumped-storage power station
underground system
construction access
layout