摘要
玉磨铁路新平隧道位于断裂破碎带中,地质条件复杂,施工过程中突泥涌水灾害频发,其突发性及规模属国内外罕见。为确保隧道工程的顺利实施,在隧道设计、施工过程中,经过研究论证、方案比选优化、现场试验和重难点技术攻关,成功解决断裂破碎带隧道施工技术难题,形成断裂破碎带含水体超前预报技术、隧道超前预加固技术、断裂带软岩大变形控制技术、带仰拱一次开挖技术、隧道非爆开挖技术等一系列关键技术成果。
The Xinping Tunnel on Yuxi-Mohan Railway is located in the fault and fracture zone with complex geological conditions.During the construction process,mud and water gushing occur frequently,which are rare around the world.Hence,in order to ensure the successful implementation of the tunnel,key construction technologies for the tunnel crossing fault and fracture zone are obtained in terms of tunnel design and construction,research and discussion,scheme comparison and optimization,field experiment and difficulty treatment.The obtained technologies include advance prediction,advance pre-reinforcement,soft rock large deformation control,one-time excavation with invert,and non-explosive excavation.
作者
赵前进
李敬伟
ZHAO Qianjin;LI Jingwei(Central South University,Changsha 410083,Hunan,China;China Railway Kunming Group Co.,Ltd.,Kunming 650011,Yunnan,China)
出处
《隧道建设(中英文)》
北大核心
2019年第12期2058-2066,共9页
Tunnel Construction
关键词
玉磨铁路新平隧道
断裂破碎带
突泥涌水
超前预报
超前预加固
大变形控制
非爆开挖
Xinping Tunnel on Yuxi-Mohan Railway
fault and fracture zone
mud and water gushing
advance prediction
advance pre-reinforcement
large deformation control
non-explosive tunneling