TBM隧洞岩溶涌水超前处置施工技术研究 被引量:4

Study of karst water gushing advance arrangement technique for TBM construction
下载PDF
导出
摘要 隧洞涌水是TBM施工中主要应对的安全风险和施工难点。结合桂中治旱乐滩水库引水灌区一期工程北干渠窑瓦~六浪隧洞工程实例,论述了TBM施工隧洞内在刀盘前方采取全断面超前分段注浆处理的方法与过程,并分析了处理效果。 Water gushing is the major safety risk and problem of TBM construction. Quyaowa-Liulang tunnel is one of the 1 st-stage works of Letan Reservoir Irrigation Project. Taking the construction of this tunnel as example, the authors discuss the method and process of full-section advance sectional grouting in front of the drill during TBM construction, and analyze the treatment effects.
作者 王松茂 甘宇程 WANG Song-mao;GAN Yu-chen(Guangdong No.2 Hydropower Engineering Company,LTD.,Guangzhou 511340,China)
出处 《广西水利水电》 2019年第6期36-38,42,共4页 Guangxi Water Resources & Hydropower Engineering
关键词 输水隧洞 TBM施工 岩溶涌水 超前注浆 桂中治旱乐滩水库引水灌区 Diversion tunnel TBM construction karst water gushing advance grouting Letan Reservoir Irrigation Area
  • 相关文献

参考文献4

二级参考文献26

共引文献117

同被引文献15

引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部