摘要
针对工业废气二氯甲烷难处理的问题,本研究提出了运用两塔串联吸收流程,采用Aspen Plus软件进行模拟计算。经过模拟计算分析,笔者确定了两吸收塔所用的吸收剂分别为N,N-二甲基甲酰胺(以下简称DMF)、水。采用严格计算模型计算可得,最终吸收塔2出口二氯甲烷、DMF废气浓度均小于5 mg/m^3。通过实验室验证,结果与计算结果基本一致,为放大设计提供了依据。
In order to solve the problem of difficult treatment of dichloromethane from industrial waste gas,a two-tower tandem absorption process was proposed and simulated by Aspen Plus software.After simulation calculation and analysis,the absorbents used in the two absorption towers are N,N-dimethylformamide(hereinafter referred to as DMF)and water.The exhaust gas concentrations of dichloromethane and DMF at the outlet of the final absorption tower 2 are less than 5 mg/m^3 by rigorous calculation model.Through laboratory verification,the results are basically consistent with the calculation results,which provides a basis for the amplification design.
作者
陈伟民
孙玉玉
李伟伟
Chen Weimin;Sun Yuyu;Li Weiwei(Nanjing Yuanheng Environmental Research Institute Co.,Ltd.;China Construction Industrial&Energy Engineering Group Co.,Ltd.,Nanjing 210009,China)
出处
《中国资源综合利用》
2019年第9期155-157,共3页
China Resources Comprehensive Utilization