摘要
以某混凝土连续箱梁大桥建设工程为依托,对主桥合龙段施工工艺及施工过程质量控制要点进行了介绍,并结合施工方案制定了施工监控方案,将监控实测值和有限元软件模拟理论值进行对比分析,确保桥梁顺利施工。
Based on the construction project of a concrete continuous box beam bridge,the construction technology,construction process and quality control points of the closure section of main bridge are introduced,and the construction monitoring scheme is formulated according to the construction scheme.The measured values of monitoring and the theoretical values of finite element software simulation are compared and analyzed to ensure the smooth construction of the bridge.
作者
刘洋
LIU Yang(Zhejiang Jiaogong Hongtu Transportation Construction Co.,Ltd.,Hangzhou 310051,China)
出处
《北方交通》
2019年第10期28-31,共4页
Northern Communications
关键词
连续梁桥
合龙段
施工技术
监控技术
Continuous beam bridge
Closure section
Construction technology
Monitoring technology