摘要 佛山国际体育文化演艺中心屋盖为大跨钢管桁架结构体系,跨长98m,总质量约为2500t,采用高空散拼施工。为确保结构由支承体系受力转变为自承力,通过在钢结构安装、焊接过程中分阶段地提前插入卸载,并使用有限元软件对卸载工况进行模拟分析,在保证结构安全的前提下应用超前卸载、延迟焊接等施工方法,达到了设计要求,取得了理想的效果。 The roof of Foshan International Sports and Cultural Performance Arts Center is a long-span steel tube truss structure system with a span of 98 m and a total mass of about 2 500 t.It is constructed by high-altitude loose assembling.To ensure that the structure is transformed from the supporting system force to self-bearing force,through beforehand inserting unloading by stages during installation and welding of steel structure,the finite element software is used to simulate and analyze the unloading condition and under the premise of ensuring the safety of structure,the construction methods of beforehand unloading and delayed welding are applied to meet the design requirements and achieve the ideal results.
作者 何健星 陈永航 姜永春 高丁丁 徐晓慧 HE Jianxing;CHEN Yonghang;JIANG Yongchun;GAO Dingding;XU Xiaohui(China Construction First Group Construction Development Co.,Ltd.,Beijing 100102,China)
出处 《建筑施工》 2019年第7期1257-1260,共4页 Building Construction
关键词 屋盖钢结构 高空散装 超前卸载 延迟焊接 roof steel structure bulk assembly at high altitude advanced unloading delayedwelding
  • 相关文献

参考文献5

二级参考文献33

共引文献37

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部