温度作用对钢箱拱桥吊装过程拱肋线形影响分析 被引量:3

Analysis on Influence of Temperature on Arch Rib Linetype during the Hoisting Process of Steel-box Arch Bridge
下载PDF
导出
摘要 钢箱拱桥在施工结束后拱肋的拱轴线线形与设计拱轴线线形的差值体现了安装精度的高低,温度作用对成桥拱轴线线形影响较大。通过对施工过程中的环境温度与设计温度不一致所导致的体系温差以及太阳光照射所导致的日照温差对各吊装节段控制点坐标的影响值的计算,提出温度作用下节段吊装控制点坐标误差的修正方法,可提高拱肋的安装精度。 The difference value of arch axis linetype and that of designed arch axis of arch rib of steel-box arch bridge after the completion of construction embodies the installation accuracy,and the influence of temperature on the arch axis linetype of completed bridge is larger.Through the calculation of influence value of temperature difference of system that is caused by the inconsistency of environment temperature and designed temperature during the construction and that of sunlight that is caused by sunlight radiation on the coordinate of control point at each hoisting section,the correction method for the error of coordinate of hoisting control point of the section under the effect of temperature is put forward,so as to improve the installation accuracy of arch rib.
作者 王建辉 黄才良 WANG Jian-hui;HUANG Cai-liang(Dalian University of Technology,Dalian 116024,China)
机构地区 大连理工大学
出处 《北方交通》 2018年第4期10-12,15,共4页 Northern Communications
关键词 钢箱拱桥 拱轴线线形控制 体系温差 日照温差 Steel-box arch bridge Linetype control of arch axis Temperature difference of system Temperature difference of sunlight
  • 相关文献

参考文献3

二级参考文献15

共引文献16

同被引文献13

引证文献3

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部