针对高桩码头施工对内河航道通航安全的影响问题,以江苏响水高桩码头工程为依托,结合工程所在水域的通航情况,分析探讨高桩码头在挖泥、打桩、预制构件吊装施工期间相应施工船舶占用水域情况。根据内河航道的船舶流量分析,提出相应的航道通航安全保证措施,确保内河航道在高桩码头施工期间航道的通畅与通航安全。
Based on the effect of high piled wharf construction on navigation safety of inland waterway,and navigation conditions of the Xiangshui high piled wharf project in Jiangsu,this paper analyzes the occupation waters of the construction vessels in different construction stages,such as dredging,piling,precast member hoisting.According to ship flow in inland waterway,it proposes the appropriate assurance measures of navigation safety,so it can ensure the channel unobstructed and navigation safety in high piled wharf construction stages.