在项目建设施工当中,采用钢板路面作为临时施工道路可以有效解决传统混凝土道路硬化养护时间长、返修损坏频率高的问题,并且钢板路面回收率高,可多次周转使用从而避免后期对临时施工道路破除造成的环境影响。钢板道路施工速度快,施工性能好,具有极高的经济效益。钢板路体系的施工方法、方案比选、施工过程控制及使用效果等方面,简要叙述钢板路体系在建设施工当中的应用情况。
Among the project construction,the use of steel as a temporary construction road pavement can effectively solve the long road hardening conventional concrete curing time,high repair damage frequency of the issue,and steel surface and high recovery,for multipl e use of working capital in order to avoid late for temporary construction roads get rid of the environmental impact caused. Steel road construction speed,good construction performance,with high economic efficiency.From construction methods steel road system,the program aspect ratio selected,the construction process control and the use of effects,and a brief description of the road system in the construction of steel construction among applications.
出处
《施工技术》
CAS
北大核心
2016年第S1期363-365,共3页
Construction Technology
关键词
建设施工
钢板路
周转
绿色施工
施工应用
building construction
plate road
turnover
green construction
testing