跨高速箱梁顶升施工技术研究 被引量:1

Study of Construction Technique for Jacking of Box Girders Crossing Expressway
下载PDF
导出
摘要 因桥下净空不足,为避免梁底局部刮擦,对混凝土连续箱梁进行调坡顶升,通过荷载计算和千斤顶配置,采取了循环顶升的方案,以保证各墩台处保持速度与位移量按比例顶升,从而避免不均匀顶升造成梁体构件的破坏。 Because of the problems form the clearance of bridge,in order to avoid local scratch of the bottom,measures for concrete continuous box girder lifting were adopted. Through the allocation of load calculation and jack,this paper takes the circular jacking scheme to ensure each pier maintain speed and displacement amount according to the proportion of top rise,so as to avoid uneven jacking caused by box girder component failure.
作者 王永 柴金玲 宁金成 WANG Yong;CHAI Jinling;NING Jincheng(He' nan Communication Vocational Technology College,Zhengzhou, He' nan 450000,Chin)
出处 《施工技术》 CAS 2018年第13期132-134,共3页 Construction Technology
基金 河南省交通运输科技项目(2018J3)
关键词 桥梁工程 箱梁 千斤顶 循环顶升 位移 施工技术 bridges box girder jack circular jacking displacement construction
  • 相关文献

参考文献6

二级参考文献20

共引文献88

同被引文献9

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部