摘要
结合郑万铁路项目CRTS Ⅰ型双块道床复测的实际案例,通过检测标架复测法与其他方法的对比,根据大量的数据分析,总结标架复测法的优劣势,在确保复测精度的同时提高轨排框架的周转使用效率,具有很强的使用价值。
Combined with the actual case of retesting CRTS I double block ballast bed in Zhengzhou-Wanzhou High-speed Railway, by comparing frame retesting method with other methods, this paper summarizes the advantages and disadvantages of frame retesting method based on a large amount of data analysis. It is of great use value to improve the turnover efficiency of rail-row frame as well as ensure the accuracy of retest.
作者
陆小利
Lu Xiaoli(China Railway 20^th Bureau Group 4^th Engineefing Co. Ltd. , Qingdao Shandong 266061, China)
出处
《铁道建筑技术》
2018年第5期119-122,共4页
Railway Construction Technology
基金
国家“十二五”科技支撑计划项目(T012000230030)