新建铁路沈阳南站中央站房屋盖采用大跨度拱形平面桁架的结构形式,通过对分段吊装与双机抬吊两种施工方案的优劣进行详细对比,最终选择了分段吊装的施工方案。通过该方案的实施,在保证施工质量与安全的同时,缩短了工期。
The central station building of New Shenyang Southern Station uses the steel truss structure with large-span arched plan. After primary determination,the segment hoisting scheme and doublemachine lifting-hanging scheme are determined. Through detailed comparison,finally,segment hoisting scheme is used. With the implementation of the scheme,the construction quality and safety are ensured,at the same time,the scheme shortens the construction period.