在小浪底引黄工程隧洞施工过程中,当发生了突涌水事故时,采取堵排水措施相结合,对采取的堵水方案进行比较,选择经济合理的方案,这些技术可为类似工程提供参考。
In the process of construction the tunnel in the Xiaolangdi Yellow River Diversion Project, when the water inrush accident occured,to take the combination of blocking and drainage measures,the comparison of water shutoff schemes was carried out,and the reasonable economic plan was seected. These technologies can provide reference for similar projects.
出处
《山西水利科技》
2017年第1期12-14,共3页
Shanxi Hydrotechnics
关键词
隧洞
断层
涌水
堵水方案
tunnel
fault
water gushing
water plugging scheme