乌鞘岭隧道整体道床病害原因分析及处理 被引量:5

The Cause and Treatment of Monolithic Track Damages of Wushaoling Tunnel
下载PDF
导出
摘要 为了彻底整治乌鞘岭隧道整体道床病害,借助雷达监测、钻孔取芯等辅助措施对病害产生的原因进行分析,并借鉴国内部分隧道采用压注聚氨酯材料抬升整体道床的成功经验对病害进行整治,取得成功。实践证明,聚氨酯注浆抬升整体道床是处理隧道道床沉降的一种简洁高效方法。 In order to thoroughly renovate the damages of monolithic tracks in Wushaoling Tunnel,the causes of track damages are analyzedby means of radar detection and core drilling,and corresponding grouting treatments with polyurethane material are successfully implemented based on the well established methods for other domestic tunnels.Practices prove that the treatment with polyurethane grouting is a simple and effective way to treat tunnel track settlement.
作者 薛再兰 XUE Zai-lan(China Railway First Survey & Design Institute Group Co. , Ltd. , Xi'an 710043, China)
出处 《铁道标准设计》 北大核心 2017年第1期85-89,共5页 Railway Standard Design
关键词 铁路隧道 特长隧道 整体道床 病害 聚氨酯 抬升 Railway tunnel Super long tunnel Monolithic track Track damages Polyurethane material Lifting
  • 相关文献

参考文献14

二级参考文献72

共引文献70

同被引文献104

引证文献5

二级引证文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部