摘要
以资江特大桥工程为依托,介绍了钢板桩围堰静压植桩法的施工技术,从钻头选型、扭矩与钻速关系两方面,对植桩机的工作参数作了探讨,有利于促进该工法的推广应用。
Taking the Zijiang super large bridge engineering as the basis,this paper introduced the construction technology of steel sheet pile cofferdam static pressure method,from the bit type selection,torque and drilling speed relationship two aspects,discussed the working parameters of pile planted machine,conducive to promoting the popularization and application of the method.