摘要
采用河道一维数学模型进行河流模拟计算,分析浑河、白塔堡河的现状防洪能力及洪水位,以此分析白塔堡河20年一遇、100年一遇洪水对浑南热电厂可能造成的淹没影响,依据相关的分析计算成果,进行洪水影响综合评价。
The one-dimensional mathematical model of river simulation is used to analysis of Hunhe River, Baita Fort river current capacity for flood control and flood level, so as to analyze the Baita Fort river once in 20 years, 100 years of the worst flood in the Hunnan thermal power plant may cause the inundation effect, on the basis of the analysis of the calculation results, influence on the comprehensive evaluation of flood.
出处
《水科学与工程技术》
2016年第1期22-25,共4页
Water Sciences and Engineering Technology
关键词
洪水
计算
评价
浑南电厂
flood
calculation
evaluation
Hunnan power plant