钢板桩围堰深填砂层高压旋喷防渗墙施工技术 被引量:6

Construction Technology of Cut-off Wall with High Pressure Jet Grouting Method for Steel Sheet Pile Cofferdam in Deep Sand Filling Stratum
下载PDF
导出
摘要 塔贝拉水电站四期扩建工程厂房下游围堰高压旋喷防渗墙是目前国内外第一例在钢板桩围堰结构形式下进行的高喷防渗工程。重点介绍了钢板桩围堰自然状态下深填砂层高喷防渗施工的关键技术、方法及防渗效果,提出了科学合理的施工方案和质量控制方法,从而保证了施工质量和工期,节约了施工成本。 The cut-off wall with high pressure jet grouting method in the lower powerhouse for phase IV project of Tarbela Hydroelectric Power Station project is the first anti-seepage project with steel sheet pile cofferdam mode by high pressure jet grouting method both in China and abroad. This paper introduces the key anti-seepage technology,method and effect with high pressure jet grouting method for steel sheet pile cofferdam in deep sand filling stratum under natural conditions,puts forward scientific and reasonable construction scheme,quality control method,which ensure construction quality and construction period,save cost.
出处 《施工技术》 CAS 北大核心 2015年第23期126-130,共5页 Construction Technology
关键词 水电站 钢板桩围堰 高压旋喷 粉细砂 防渗墙 施工技术 hydroelectric power stations steel sheet pile cofferdam high pressure jet grouting fine sand cut-off wall construction
  • 相关文献

参考文献7

二级参考文献5

共引文献18

同被引文献23

引证文献6

二级引证文献21

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部